07 Project Management and Where Value Is Earned

RecalibrateLab: Two earned-value curvesFeeds M2, M3P5

Load-bearing assumption

Progress is measured by work completed

Verdict: Recalibrate

Earned value rests on objective completion criteria, which for software already means accepted work; agents widen the gap between generated and accepted work, so each project must state its credit event, and for agent work I set it at verified merge.

Learning objectives

After this chapter you should be able to:

  1. Build a work breakdown structure that satisfies the 100% rule, and find the critical path and float of a small network.
  2. Compute planned value, earned value, actual cost, the variances and indices, and the estimate at completion.
  3. State the load-bearing assumption of earned value, and distinguish rigorous completion criteria, the informal shortcut of crediting at ticket close, and the new conditions that make the shortcut costly.
  4. Distinguish code-complete, merge-ready and integrated work, and explain why the critical path runs through review.
  5. Size work packages, state a project's credit event, and track the review-state gap.
  6. Test the verdict (prediction P5) on your own project data.

Opening case

A composite case, not a real engagement.

Ines is a program manager for three internal software projects. Each month a status agent builds her earned-value report from the team's ticket tracker: a work package counts as complete when its ticket is closed, and a ticket closes when the implementing agent opens a pull request and reports that its tests pass.

The chapter continues from here.

What the chapter covers

  1. 7.1 The classical method
    • 7.1.1 Project, product and program
    • 7.1.2 The work breakdown structure
    • 7.1.3 The critical path method
    • 7.1.4 Earned value management
    • 7.1.5 The agile counterparts
    • 7.1.6 What the classical method got right
  2. 7.2 The assumption it depends on
  3. 7.3 What agents change
    • 7.3.1 Generated is not verified
    • 7.3.2 What survives: the structure and the critical path
    • 7.3.3 Program management returns
  4. 7.4 The verdict
  5. 7.5 What replaces it: earned value at verified merge
    • 7.5.1 The rules
    • 7.5.2 The Dispatch plan
    • 7.5.3 Nine weeks, two ways
    • 7.5.4 The gap as a leading indicator
    • 7.5.5 Burndown at merge
  6. 7.6 Lab: Two earned-value curves
  7. 7.7 What would make this verdict false

Lab and prediction

Lab: Two earned-value curves

Feeds milestone M2 (BAC); M3 (WBS, tracking). How the labs fit the project

The lab tests this prediction from the working paper the book grows from (Smith 2026a):

  • P5 Earned value at code-complete and at verified merge diverge, most in weeks of highest agent output

A result that contradicts a prediction, honestly reported, is a result. You are graded on accurate records and reasoned interpretation, not on agreeing with the book.

Summary

  • Load-bearing assumption: progress is measured by work completed. Rigorous EVM credits against objective criteria set in advance; crediting at ticket close was a shortcut, tolerable only while φ was small and the reporter was the worker.
  • Verdict: recalibrate. The equations survive. Each project states its credit event, packages are sized to one agent session and one review sitting, and the critical path runs through the reviewer's calendar.
  • Replacement: for Dispatch, credit at verified merge, all or nothing, with a named acceptance check, three tracked states and the review-state gap as a leading indicator.
  • Worked result: on Dispatch (BAC 105 hours), the week-4 generation view forecasts 76 hours and the merge view 126; the project finished at 118. No study yet computes earned value both ways (prediction P5).
  • Earned value is budgeted work accepted, not demonstrated customer value, and a project-management agent must read the repository, never other agents' claims.

Key terms

Credit event
the stated event at which a work package earns its budget.Also used in 2
Verified merge
arrival of the integrated state; the credit event used for Dispatch.Also used in 2, 16
Code-complete, merge-ready, integrated
an agent reports done; reviewed and acceptance check passed; merged and main line green. (Hassan's third rung is "integration-ready": Hassan 2026, §6.4.4, p. 192.)Also used in 1, 2, 3, 18
Review-state gap
packages generated but not yet integrated.
φ (phi)
the share of a package's budgeted effort that remains after the point where it is credited.Also used in 1, 2, 3, 4, 5, 6, 8, 9, 10, 11, 12, 13, 14, 15, 16, 17, 18
Demonstrated customer value
value shown in use after release, as distinct from budgeted value earned.Also used in 2
WBS, work package, 100% rule
a decomposition of scope; its lowest element; child elements account for exactly 100% of their parent (Haugan 2002).Also used in 2, 5, 9, 14
BAC, PV, EV, AC, SPI, CPI, EAC
the quantities and indices of Section 7.1.4.

Connections

Where this chapter and another point to each other most often.

See it on the map

Further reading

  • Brooks (1975), The Mythical Man-Month, chapter 14, pp. 154–155. The best argument for objective definitions of done.
  • Kelley and Walker (1959). The original critical-path paper.
  • Fleming and Koppelman (2010), Earned Value Project Management. The equations and their use in forecasting.
  • Li et al. (2025) and Peralta et al. (2026). Two large studies of agent pull requests; read the second for what a merge or rejection does and does not tell you.